ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0155 · BESS · Franklin County

Lupinus Storage 2

Lupinus Storage 2 is a 124 MW battery storage project in Franklin County, Texas, connecting at Hagansport Switch (old Monticello Tap bus# 1794). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/03/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0155
Capacity
124 MW
Fuel
BESS (BA)
Interconnecting entity
Lupinus Solar 2, LLC
Projected COD
04/03/2027
Entered queue
12/13/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/17/2026
    FIS Requested → FIS Approved
  • 03/04/2025
    FIS Approved → IA Signed
  • 05/11/2022
    Screening → FIS Requested
  • 12/13/2021
    Entered the queue with 124 MW, projected COD 04/03/2027

Other projects at this substation

Lupinus Solar 2Solar242 MWIA Signed