24INR0153 · BESS · Franklin County
Lupinus Storage 1
Lupinus Storage 1 is a 84 MW battery storage project in Franklin County, Texas, connecting at Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 09/13/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0153
- Capacity
- 84 MW
- Fuel
- BESS (BA)
- County
- Franklin County
- Interconnecting entity
- Lupinus Solar, LLC
- Projected COD
- 09/13/2027
- Entered queue
- 12/13/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/17/2026FIS Requested → FIS Approved
- 05/11/2022Screening → FIS Requested
- 12/13/2021Entered the queue with 84 MW, projected COD 09/13/2027
Other projects at this substation
| Lupinus Solar 1 | Solar | 162 MW | IA Signed |