24INR0131 · BESS · Zapata County
Zelus BESS
Zelus BESS is a 201 MW battery storage project in Zapata County, Texas, connecting at the 138 kV Zapata Substation (#8299; AEP). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0131
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Zapata County
- Interconnecting entity
- BRP Zelus BESS LLC
- Projected COD
- 12/01/2027
- Entered queue
- 12/03/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/03/2021Entered the queue with 201 MW, projected COD 12/01/2027
- 12/03/2021Screening → FIS Requested