Val Vista Grid BESS 2 is a 211 MW battery storage project in Hidalgo County, Texas, connecting at Tap 345kV 8383 North Edinburg - 80137 Stewart Road. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0102
Capacity
211 MW
Fuel
BESS (BA)
Interconnecting entity
Val Vista Grid, LLC
Projected COD
03/30/2029
Entered queue
10/01/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/31/2025
    FIS Requested → IA Signed
  • 10/01/2021
    Entered the queue with 211 MW, projected COD 03/30/2029
  • 10/01/2021
    Screening → FIS Requested

Other projects at this substation

Val Vista Grid BESS 1BESS209 MWIA Signed