24INR0087 · BESS · Navarro County
Pisgah Ridge Storage 3
Pisgah Ridge Storage 3 is a 101 MW battery storage project in Navarro County, Texas, connecting at Tap 345kV 68091 Navarro - 46020 Limestone. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0087
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- County
- Navarro County
- Interconnecting entity
- Pisgah Ridge 3, LLC
- Projected COD
- 03/31/2029
- Entered queue
- 07/14/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/25/2021Screening → FIS Requested
- 07/14/2021Entered the queue with 101 MW, projected COD 03/31/2029
Other projects at this substation
| Pisgah Ridge Solar 2 | Solar | 102 MW | FIS Requested |