24INR0087 · BESS · Navarro County

Pisgah Ridge Storage 3

Pisgah Ridge Storage 3 is a 101 MW battery storage project in Navarro County, Texas, connecting at Tap 345kV 68091 Navarro - 46020 Limestone. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0087
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
Pisgah Ridge 3, LLC
Projected COD
03/31/2029
Entered queue
07/14/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/25/2021
    Screening → FIS Requested
  • 07/14/2021
    Entered the queue with 101 MW, projected COD 03/31/2029

Other projects at this substation

Pisgah Ridge Solar 2Solar102 MWFIS Requested