24INR0069 · Solar · Lampasas County
Triple B Solar Alt#2
Triple B Solar Alt#2 is a 150 MW solar project in Lampasas County, Texas, connecting at Tap 138kV 7066 Adamsville - 7064 Lampasas. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0069
- Capacity
- 150 MW
- Fuel
- Solar (PV)
- County
- Lampasas County
- Interconnecting entity
- Triple B Solar LLC
- Projected COD
- 07/01/2028
- Entered queue
- 06/10/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/15/2021Screening → FIS Requested
- 06/10/2021Entered the queue with 150 MW, projected COD 07/01/2028
Other projects at this substation
No other projects at this substation.