24INR0066 · BESS · Goliad County
Keys Hollow Storage Phase II SLF
Keys Hollow Storage Phase II SLF is a 0 MW battery storage project in Goliad County, Texas, connecting at 345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/10/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0066
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Goliad County
- Interconnecting entity
- Keys Hollow Solar, LLC
- Projected COD
- 03/10/2028
- Entered queue
- 06/17/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/29/2024FIS Requested → IA Signed
- 01/10/2022Screening → FIS Requested
- 06/17/2021Entered the queue with 0 MW, projected COD 03/10/2028
Other projects at this substation
| Keys Hollow Solar Phase II SLF | Solar | 201 MW | IA Signed |