24INR0042 · Solar · Milam County
Yaupon Solar SLF
Yaupon Solar SLF is a 201 MW solar project in Milam County, Texas, connecting at Tap 345 kV Gibson Switch (3706) – TNP One (39950). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/18/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0042
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Milam County
- Interconnecting entity
- Yaupon Solar, LLC
- Projected COD
- 11/18/2026
- Entered queue
- 03/30/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/13/2026Energization Approved → Sync Approved
- 05/27/2026IA Signed → Energization Approved
- 09/16/2025FIS Requested → FIS Approved
- 09/28/2023FIS Approved → IA Signed
- 11/23/2021Screening → FIS Requested
- 03/30/2021Entered the queue with 201 MW, projected COD 11/18/2026
Other projects at this substation