LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0042 · Solar · Milam County

Yaupon Solar SLF

Yaupon Solar SLF is a 201 MW solar project in Milam County, Texas, connecting at Tap 345 kV Gibson Switch (3706) – TNP One (39950). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/18/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0042
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Yaupon Solar, LLC
Projected COD
11/18/2026
Entered queue
03/30/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2026
    Energization Approved → Sync Approved
  • 05/27/2026
    IA Signed → Energization Approved
  • 09/16/2025
    FIS Requested → FIS Approved
  • 09/28/2023
    FIS Approved → IA Signed
  • 11/23/2021
    Screening → FIS Requested
  • 03/30/2021
    Entered the queue with 201 MW, projected COD 11/18/2026