23INR0556 · BESS · Fort Bend County
IEP Orchard BESS
COD delayed 1×
IEP Orchard BESS is a 10 MW battery storage project in Fort Bend County, Texas, connecting at Station Name (TDSP Station Code): OR. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0556
- Capacity
- 10 MW
- Fuel
- BESS (BA)
- Substation
- Station Name (TDSP Station Code): OR
- County
- Fort Bend County
- Interconnecting entity
- IEP Tejas Verde LLC
- Projected COD
- 12/31/2027
- Entered queue
- 08/09/2023
- ERCOT zone
- HOUSTON
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/18/2026 → 12/31/2027 (+15 months)
- 12/06/2024Energization Approved → Sync Approved
- 11/12/2024IA Signed → Energization Approved
- 08/09/2023Entered the queue with 10 MW, projected COD 09/18/2026
- 08/09/2023Screening → IA Signed
Other projects at this substation