23INR0529 · BESS · Webb County

Torrecillas BESS

Torrecillas BESS is a 9.9 MW battery storage project in Webb County, Texas, connecting at 161257 Torrecillas 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0529
Capacity
9.9 MW
Fuel
BESS (BA)
Interconnecting entity
Torrecillas Interconnect, LLC
Projected COD
12/31/2026
Entered queue
01/30/2015
ERCOT zone
SOUTH
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/01/2025
    Energization Approved → Sync Approved
  • 06/25/2025
    IA Signed → Energization Approved
  • 01/30/2015
    Entered the queue with 9.9 MW, projected COD 12/31/2026
  • 01/30/2015
    Screening → IA Signed

Other projects at this substation