23INR0501 · BESS · Crane County

Soda Lake BESS 1

Withdrawn

Soda Lake BESS 1 is a 204 MW battery storage project in Crane County, Texas, connecting at 138kV Soda Lake Substation (#76026). It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0501
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
Mendoza Trail BESS, LLC
Projected COD
08/15/2026
Entered queue
08/20/2018
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Listed as withdrawn UNCONFIRMED
  • 11/05/2025
    Energization Approved → Sync Approved
  • 09/02/2025
    IA Signed → Energization Approved
  • 10/22/2024
    FIS Requested → FIS Approved
  • 08/09/2022
    Screening → FIS Requested
  • 08/20/2018
    Entered the queue with 204 MW, projected COD 08/15/2026
  • 08/20/2018
    FIS Approved → IA Signed