23INR0466 · BESS · Matagorda County
Shoshana Storage
Shoshana Storage is a 221 MW battery storage project in Matagorda County, Texas, connecting at Tap STP – Refuge ckt 27. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0466
- Capacity
- 221 MW
- Fuel
- BESS (BA)
- Substation
- Tap STP – Refuge ckt 27
- County
- Matagorda County
- Interconnecting entity
- Shoshana Storage Project LLC
- Projected COD
- 05/30/2028
- Entered queue
- 03/30/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/16/2022Screening → FIS Requested
- 03/30/2022Entered the queue with 221 MW, projected COD 05/30/2028
Other projects at this substation
No other projects at this substation.