23INR0462 · BESS · Hidalgo County

Palladium Storage

Palladium Storage is a 156 MW battery storage project in Hidalgo County, Texas, connecting at Tap 138 kV 8656 Luna - 8033 Pantera. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0462
Capacity
156 MW
Fuel
BESS (BA)
Interconnecting entity
Palladium Energy Storage LLC
Projected COD
06/30/2028
Entered queue
01/21/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/21/2022
    Entered the queue with 156 MW, projected COD 06/30/2028
  • 01/21/2022
    Screening → FIS Requested