23INR0456 · BESS · Hidalgo County
Bronze Quinta Storage
Bronze Quinta Storage is a 104 MW battery storage project in Hidalgo County, Texas, connecting at S_MCALLN 8371 (S. McAllen 138kV Substation). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0456
- Capacity
- 104 MW
- Fuel
- BESS (BA)
- County
- Hidalgo County
- Interconnecting entity
- KCE TX 28, LLC
- Projected COD
- 01/01/2028
- Entered queue
- 01/11/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/11/2022Entered the queue with 104 MW, projected COD 01/01/2028
- 01/11/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.