LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0392 · BESS · Bee County

Honeycomb Storage SLF

Honeycomb Storage SLF is a 0 MW battery storage project in Bee County, Texas, connecting at 69 kV Tynan Substation (#8107). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/11/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0392
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
Honeycomb BESS, LLC
Projected COD
05/11/2027
Entered queue
11/02/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/28/2025
    FIS Requested → FIS Approved
  • 05/01/2023
    FIS Approved → IA Signed
  • 11/02/2021
    Entered the queue with 0 MW, projected COD 05/11/2027
  • 11/02/2021
    Screening → FIS Requested

Other projects at this substation

Honeycomb Solar SLFSolar61 MWIA Signed