23INR0368 · Solar · Parker County
Rocking X Solar
Rocking X Solar is a 602 MW solar project in Parker County, Texas, connecting at Tap the 345 kV Parker Switch (bus#1436) – Comanche Peak SES (bus#1900) Double-Circuit line, Circuit 1.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/20/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0368
- Capacity
- 602 MW
- Fuel
- Solar (PV)
- County
- Parker County
- Interconnecting entity
- 7100 Tin Top LLC
- Projected COD
- 09/20/2027
- Entered queue
- 09/06/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/06/2023Entered the queue with 602 MW, projected COD 09/20/2027
- 09/06/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.