LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0330 · BESS · Briscoe County

BRP Snowdon BESS

BRP Snowdon BESS is a 411 MW battery storage project in Briscoe County, Texas, connecting at 23914 Tule Canyon Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0330
Capacity
411 MW
Fuel
BESS (BA)
Interconnecting entity
BRP SNOWDON BESS LLC
Projected COD
12/01/2028
Entered queue
09/08/2021
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/08/2021
    Entered the queue with 411 MW, projected COD 12/01/2028
  • 09/08/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.