23INR0308 · BESS · Crane County
Fowler Ranch Storage
COD delayed 1×
Fowler Ranch Storage is a 26 MW battery storage project in Crane County, Texas, connecting at 76025 Castle Mountain 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0308
- Capacity
- 26 MW
- Fuel
- BESS (BA)
- Substation
- 76025 Castle Mountain 138kV
- County
- Crane County
- Interconnecting entity
- Crane BESS, LLC
- Projected COD
- 09/30/2027
- Entered queue
- 06/21/2021
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 06/30/2027 → 09/30/2027 (+3 months)
- 05/18/2022Screening → FIS Requested
- 06/21/2021Entered the queue with 26 MW, projected COD 06/30/2027
Other projects at this substation
No other projects at this substation.