ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0286 · Solar · Rusk County

Dry Creek Solar I

Dry Creek Solar I is a 201 MW solar project in Rusk County, Texas, connecting at tap 345kV 3100 Martin Lake - 3105 Elkton. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 01/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0286
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
OAK HILL SOLAR LLC
Projected COD
01/31/2026
Entered queue
08/18/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/19/2025
    Energization Approved → Sync Approved
  • 05/08/2025
    IA Signed → Energization Approved
  • 06/12/2024
    FIS Requested → FIS Approved
  • 11/02/2023
    FIS Approved → IA Signed
  • 03/30/2022
    Screening → FIS Requested
  • 08/18/2021
    Entered the queue with 201 MW, projected COD 01/31/2026

Other projects at this substation

No other projects at this substation.