ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0278 · BESS · Andrews County

Tucana BESS

Tucana BESS is a 201 MW battery storage project in Andrews County, Texas, connecting at 1157 Andrews County South 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0278
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Tucana BESS LLC
Projected COD
03/01/2028
Entered queue
05/10/2021
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/18/2025
    FIS Requested → FIS Approved
  • 05/10/2021
    Entered the queue with 201 MW, projected COD 03/01/2028
  • 05/10/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.