23INR0249 · Solar · Bell County
Limewood Solar
Limewood Solar is a 205 MW solar project in Bell County, Texas, connecting at 3420 Temple Pecan Creek 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/29/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0249
- Capacity
- 205 MW
- Fuel
- Solar (PV)
- Substation
- 3420 Temple Pecan Creek 138kV
- County
- Bell County
- Interconnecting entity
- Limewood Bell Renewables, LLC
- Projected COD
- 12/29/2026
- Entered queue
- 04/30/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/15/2026Energization Approved → Sync Approved
- 08/10/2026IA Signed → Energization Approved
- 03/14/2025FIS Requested → FIS Approved
- 02/22/2023FIS Approved → IA Signed
- 10/06/2021Screening → FIS Requested
- 04/30/2021Entered the queue with 205 MW, projected COD 12/29/2026
Other projects at this substation
| Limewood Storage | BESS | 50 MW | IA Signed |