ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0249 · Solar · Bell County

Limewood Solar

Limewood Solar is a 205 MW solar project in Bell County, Texas, connecting at 3420 Temple Pecan Creek 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/29/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0249
Capacity
205 MW
Fuel
Solar (PV)
Interconnecting entity
Limewood Bell Renewables, LLC
Projected COD
12/29/2026
Entered queue
04/30/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2026
    Energization Approved → Sync Approved
  • 08/10/2026
    IA Signed → Energization Approved
  • 03/14/2025
    FIS Requested → FIS Approved
  • 02/22/2023
    FIS Approved → IA Signed
  • 10/06/2021
    Screening → FIS Requested
  • 04/30/2021
    Entered the queue with 205 MW, projected COD 12/29/2026