23INR0232 · BESS · Gonzales County
Hoke Storage
Hoke Storage is a 33 MW battery storage project in Gonzales County, Texas, connecting at tap 138kV 7595 Deer Creek - 7621 Nixon. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/05/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0232
- Capacity
- 33 MW
- Fuel
- BESS (BA)
- Substation
- tap 138kV 7595 Deer Creek - 7621 Nixon
- County
- Gonzales County
- Interconnecting entity
- Hoke Solar Project, LLC
- Projected COD
- 07/05/2027
- Entered queue
- 04/22/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/17/2026FIS Requested → FIS Approved
- 04/25/2022FIS Approved → IA Signed
- 04/22/2021Entered the queue with 33 MW, projected COD 07/05/2027
- 04/22/2021Screening → FIS Requested
Other projects at this substation
| Hoke Solar | Solar | 95 MW | IA Signed |