LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0209 · BESS · Webb County

Outpost Storage

Outpost Storage is a 508 MW battery storage project in Webb County, Texas, connecting at 345kv Avanzada7A (80235). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0209
Capacity
508 MW
Fuel
BESS (BA)
Interconnecting entity
Hecate Energy Outpost Storage LLC
Projected COD
03/01/2028
Entered queue
02/15/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/15/2021
    Entered the queue with 508 MW, projected COD 03/01/2028
  • 02/15/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.