23INR0202 · Solar · Erath County
Erath County Solar
Erath County Solar is a 207 MW solar project in Erath County, Texas, connecting at tap 345kV 68020 Romney1E - 68030 KopperlW. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0202
- Capacity
- 207 MW
- Fuel
- Solar (PV)
- County
- Erath County
- Interconnecting entity
- Erath County Solar, LLC
- Projected COD
- 01/31/2029
- Entered queue
- 03/06/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/01/2023FIS Requested → IA Signed
- 03/06/2021Entered the queue with 207 MW, projected COD 01/31/2029
- 03/06/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.