23INR0168 · BESS · Matagorda County
Charolais Storage
Withdrawn
Charolais Storage is a 150 MW battery storage project in Matagorda County, Texas, connecting at tap 345kV 44000 W A Parish - 5915 STP. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0168
- Capacity
- 150 MW
- Fuel
- BESS (BA)
- Substation
- tap 345kV 44000 W A Parish - 5915 STP
- County
- Matagorda County
- Interconnecting entity
- RWE Solar Development, LLC
- Projected COD
- 12/15/2026
- Entered queue
- 02/09/2021
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/14/2026Listed as cancelled
- 06/11/2021Screening → FIS Requested
- 02/09/2021Entered the queue with 150 MW, projected COD 12/15/2026
Other projects at this substation
| Charolais Solar | Solar | 262 MW | Withdrawn |