23INR0137 · BESS · Wharton County

Diran BESS

Diran BESS is a 103 MW battery storage project in Wharton County, Texas, connecting at 43190 South Lane City 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0137
Capacity
103 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Diran BESS LLC
Projected COD
01/31/2028
Entered queue
11/25/2020
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/03/2025
    FIS Requested → FIS Approved
  • 01/07/2025
    FIS Approved → IA Signed
  • 11/25/2020
    Entered the queue with 103 MW, projected COD 01/31/2028
  • 11/25/2020
    Screening → FIS Requested