23INR0126 · BESS · Harris County

Sigma Storage

Sigma Storage is a 408 MW battery storage project in Harris County, Texas, connecting at 40460 Deepwater 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0126
Capacity
408 MW
Fuel
BESS (BA)
Interconnecting entity
AES Distributed Energy, Inc
Projected COD
10/01/2029
Entered queue
05/11/2021
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/04/2022
    Screening → FIS Requested
  • 05/11/2021
    Entered the queue with 408 MW, projected COD 10/01/2029