23INR0091 · Solar · Brazoria County
Cascade Solar
Cascade Solar is a 171 MW solar project in Brazoria County, Texas, connecting at 43180 SAVANAH 345 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0091
- Capacity
- 171 MW
- Fuel
- Solar (PV)
- Substation
- 43180 SAVANAH 345 kV
- County
- Brazoria County
- Interconnecting entity
- Cascade Solar Energy, LLC
- Projected COD
- 01/15/2028
- Entered queue
- 02/09/2021
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/02/2025FIS Requested → FIS Approved
- 04/17/2023FIS Approved → IA Signed
- 04/28/2021Screening → FIS Requested
- 02/09/2021Entered the queue with 171 MW, projected COD 01/15/2028
Other projects at this substation
No other projects at this substation.