23INR0086 · Solar · Coleman County
Hanson Solar
Hanson Solar is a 399 MW solar project in Coleman County, Texas, connecting at tap 345kV 1444 Brown - 11406 Central Bluff. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/17/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0086
- Capacity
- 399 MW
- Fuel
- Solar (PV)
- County
- Coleman County
- Interconnecting entity
- Hanson Solar, LLC
- Projected COD
- 08/17/2027
- Entered queue
- 10/23/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/26/2026FIS Requested → FIS Approved
- 09/20/2023FIS Approved → IA Signed
- 03/25/2021Screening → FIS Requested
- 10/23/2020Entered the queue with 399 MW, projected COD 08/17/2027
Other projects at this substation
No other projects at this substation.