Shaw Solar is a 125 MW solar project in Bandera County, Texas, connecting at Tap 138kV 7146 Verde Creek - 7438 Bandera. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/16/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0078
Capacity
125 MW
Fuel
Solar (PV)
Interconnecting entity
Rio Lago Solar, LLC
Projected COD
10/16/2026
Entered queue
10/23/2020
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/31/2026
    Energization Approved → Sync Approved
  • 06/04/2026
    IA Signed → Energization Approved
  • 03/12/2025
    FIS Requested → FIS Approved
  • 02/17/2023
    FIS Approved → IA Signed
  • 05/11/2021
    Screening → FIS Requested
  • 10/23/2020
    Entered the queue with 125 MW, projected COD 10/16/2026