ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0059 · Solar · Haskell County

Briggs Solar

Briggs Solar is a 324 MW solar project in Haskell County, Texas, connecting at tap 345kV 60515 Clear Crossing - 60507 Pendulo. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0059
Capacity
324 MW
Fuel
Solar (PV)
Interconnecting entity
IP Quantum III, LLC
Projected COD
04/15/2028
Entered queue
08/04/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/15/2025
    FIS Requested → IA Signed
  • 03/04/2021
    Screening → FIS Requested
  • 08/04/2020
    Entered the queue with 324 MW, projected COD 04/15/2028

Other projects at this substation

Briggs StorageBESS336 MWIA Signed