ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0058 · Solar · Wharton County

Erin Solar

Erin Solar is a 208 MW solar project in Wharton County, Texas, connecting at 44040 Bailey 345 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0058
Capacity
208 MW
Fuel
Solar (PV)
Interconnecting entity
Erin Solar LLC
Projected COD
12/31/2029
Entered queue
07/24/2020
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/22/2023
    FIS Requested → IA Signed
  • 01/26/2021
    Screening → FIS Requested
  • 07/24/2020
    Entered the queue with 208 MW, projected COD 12/31/2029

Other projects at this substation

Peach Creek SolarSolar300 MWFIS Requested