23INR0057 · Solar · Matagorda County
Duffy Solar
Duffy Solar is a 502 MW solar project in Matagorda County, Texas, connecting at Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0057
- Capacity
- 502 MW
- Fuel
- Solar (PV)
- County
- Matagorda County
- Interconnecting entity
- Duffy Project Co LLC
- Projected COD
- 12/31/2027
- Entered queue
- 09/11/2020
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/12/2023FIS Requested → IA Signed
- 02/04/2021Screening → FIS Requested
- 09/11/2020Entered the queue with 502 MW, projected COD 12/31/2027
Other projects at this substation
| Duffy BESS | BESS | 241 MW | IA Signed |