ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0056 · Solar · Deaf Smith County

Caliche Mound Solar

Caliche Mound Solar is a 407 MW solar project in Deaf Smith County, Texas, connecting at Mule Deer Switch 23921 (tap 345kV 23906 AJSwope - 23910 Windmill). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/26/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0056
Capacity
407 MW
Fuel
Solar (PV)
Interconnecting entity
CIG DS1 LLC
Projected COD
10/26/2027
Entered queue
07/07/2020
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/17/2026
    FIS Requested → FIS Approved
  • 10/12/2023
    FIS Approved → IA Signed
  • 07/07/2020
    Entered the queue with 407 MW, projected COD 10/26/2027
  • 07/07/2020
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.