ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0015 · Solar · Castro County

Scarlet Solar

COD date passed

Scarlet Solar is a 180 MW solar project in Castro County, Texas, connecting at tap 345kV 23912 Ogallala - 23910 Windmill. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/26/2025. Its projected COD of 08/26/2025 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0015
Capacity
180 MW
Fuel
Solar (PV)
Interconnecting entity
Innovative Solar 416, LLC
Projected COD
08/26/2025
Entered queue
12/11/2019
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/31/2020
    Screening → FIS Requested
  • 12/11/2019
    Entered the queue with 180 MW, projected COD 08/26/2025

Other projects at this substation

No other projects at this substation.