Sierra Madre Solar is a 255 MW solar project in Zapata County, Texas, connecting at tap 345kV 80307 Del Sol - 80225 Cenizo. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0006
- Capacity
- 255 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 80307 Del Sol - 80225 Cenizo
- County
- Zapata County
- Interconnecting entity
- Sierra Madre Solar LLC
- Projected COD
- 12/01/2027
- Entered queue
- 01/22/2020
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/05/2020Screening → FIS Requested
- 01/22/2020Entered the queue with 255 MW, projected COD 12/01/2027