22INR0558 · BESS · Harris County
Callisto II Energy Center
COD delayed 1×
Callisto II Energy Center is a 203 MW battery storage project in Harris County, Texas, connecting at 47150 HO Clarke 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/17/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0558
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- Substation
- 47150 HO Clarke 138kV
- County
- Harris County
- Interconnecting entity
- Callisto II Energy Center LLC
- Projected COD
- 12/17/2026
- Entered queue
- 09/29/2021
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2026 → 12/17/2026 (+3 months)
- 08/21/2025FIS Requested → FIS Approved
- 12/11/2023FIS Approved → IA Signed
- 09/29/2021Entered the queue with 203 MW, projected COD 10/01/2026
- 09/29/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.