LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0558 · BESS · Harris County

Callisto II Energy Center

COD delayed 1×

Callisto II Energy Center is a 203 MW battery storage project in Harris County, Texas, connecting at 47150 HO Clarke 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/17/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0558
Capacity
203 MW
Fuel
BESS (BA)
Interconnecting entity
Callisto II Energy Center LLC
Projected COD
12/17/2026
Entered queue
09/29/2021
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2026 → 12/17/2026 (+3 months)
  • 08/21/2025
    FIS Requested → FIS Approved
  • 12/11/2023
    FIS Approved → IA Signed
  • 09/29/2021
    Entered the queue with 203 MW, projected COD 10/01/2026
  • 09/29/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.