22INR0552 · BESS · Kaufman County
Sowers Storage
Sowers Storage is a 209 MW battery storage project in Kaufman County, Texas, connecting at 6894 Rose Hill_RC Sub 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0552
- Capacity
- 209 MW
- Fuel
- BESS (BA)
- Substation
- 6894 Rose Hill_RC Sub 138 kV
- County
- Kaufman County
- Interconnecting entity
- Sowers Energy Storage LLC
- Projected COD
- 07/01/2027
- Entered queue
- 08/18/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/22/2022FIS Requested → IA Signed
- 08/18/2021Entered the queue with 209 MW, projected COD 07/01/2027
- 08/18/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.