LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0517 · Wind · Wharton County

Lane City Wind

Lane City Wind is a 200 MW wind project in Wharton County, Texas, connecting at 44040 Bailey 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0517
Capacity
200 MW
Fuel
Wind (WT)
Interconnecting entity
RWE Clean Energy, LLC
Projected COD
12/31/2026
Entered queue
04/26/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/28/2025
    Energization Approved → Sync Approved
  • 06/12/2025
    IA Signed → Energization Approved
  • 07/18/2024
    FIS Requested → FIS Approved
  • 05/13/2022
    FIS Approved → IA Signed
  • 04/26/2021
    Entered the queue with 200 MW, projected COD 12/31/2026
  • 04/26/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.