22INR0517 · Wind · Wharton County
Lane City Wind
Lane City Wind is a 200 MW wind project in Wharton County, Texas, connecting at 44040 Bailey 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0517
- Capacity
- 200 MW
- Fuel
- Wind (WT)
- Substation
- 44040 Bailey 345kV
- County
- Wharton County
- Interconnecting entity
- RWE Clean Energy, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 04/26/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/28/2025Energization Approved → Sync Approved
- 06/12/2025IA Signed → Energization Approved
- 07/18/2024FIS Requested → FIS Approved
- 05/13/2022FIS Approved → IA Signed
- 04/26/2021Entered the queue with 200 MW, projected COD 12/31/2026
- 04/26/2021Screening → FIS Requested
Other projects at this substation