ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0385 · BESS · Crane County

BRP Pictor BESS

COD delayed 1×

BRP Pictor BESS is a 201 MW battery storage project in Crane County, Texas, connecting at 60400 Lynx 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0385
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Pictor BESS LLC
Projected COD
12/31/2029
Entered queue
07/24/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 11/01/2025 → 12/31/2029 (+50 months)
  • 08/13/2020
    Screening → FIS Requested
  • 07/24/2020
    Entered the queue with 201 MW, projected COD 11/01/2025

Other projects at this substation

No other projects at this substation.