22INR0385 · BESS · Crane County
BRP Pictor BESS
COD delayed 1×
BRP Pictor BESS is a 201 MW battery storage project in Crane County, Texas, connecting at 60400 Lynx 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0385
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 60400 Lynx 138kV
- County
- Crane County
- Interconnecting entity
- BRP Pictor BESS LLC
- Projected COD
- 12/31/2029
- Entered queue
- 07/24/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 11/01/2025 → 12/31/2029 (+50 months)
- 08/13/2020Screening → FIS Requested
- 07/24/2020Entered the queue with 201 MW, projected COD 11/01/2025