22INR0383 · BESS · Reagan County

BRP Musca BESS

BRP Musca BESS is a 100 MW battery storage project in Reagan County, Texas, connecting at 60361 Santa Rita 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0383
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Musca BESS LLC
Projected COD
12/01/2027
Entered queue
07/24/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2020
    Screening → FIS Requested
  • 07/24/2020
    Entered the queue with 100 MW, projected COD 12/01/2027

Other projects at this substation

No other projects at this substation.