22INR0262 · Solar · Callahan County
Sequoia II Solar
COD delayed 1×
Sequoia II Solar is a 418 MW solar project in Callahan County, Texas, connecting at 68051 Reata 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/28/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0262
- Capacity
- 418 MW
- Fuel
- Solar (PV)
- Substation
- 68051 Reata 345kV
- County
- Callahan County
- Interconnecting entity
- ENBRIDGE SOLAR SEQUOIA II LLC
- Projected COD
- 01/28/2027
- Entered queue
- 01/22/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 11/21/2026 → 01/28/2027 (+2 months)
- 03/16/2026FIS Requested → FIS Approved
- 08/29/2023FIS Approved → IA Signed
- 08/27/2020Screening → FIS Requested
- 01/22/2020Entered the queue with 418 MW, projected COD 11/21/2026
Other projects at this substation
No other projects at this substation.