22INR0220 · Solar · Comanche County
Lamkin Solar
COD delayed 1×
Lamkin Solar is a 102 MW solar project in Comanche County, Texas, connecting at tap 69kV 258 Hamilton - 273 Gustine. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/08/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0220
- Capacity
- 102 MW
- Fuel
- Solar (PV)
- Substation
- tap 69kV 258 Hamilton - 273 Gustine
- County
- Comanche County
- Interconnecting entity
- Commanche Solar, LLC
- Projected COD
- 11/08/2027
- Entered queue
- 06/24/2019
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/08/2027 → 11/08/2027 (+3 months)
- 03/06/2025FIS Approved → IA Signed
- 07/11/2022FIS Requested → FIS Approved
- 03/13/2020Screening → FIS Requested
- 06/24/2019Entered the queue with 102 MW, projected COD 08/08/2027