22INR0205 · Solar · Wharton County
Sbranch Solar
Sbranch Solar is a 234 MW solar project in Wharton County, Texas, connecting at Tap 138kV 44190 East Bernard - 44130 Caney. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0205
- Capacity
- 234 MW
- Fuel
- Solar (PV)
- County
- Wharton County
- Interconnecting entity
- Bernard Creek Solar, LLC
- Projected COD
- 10/31/2026
- Entered queue
- 01/03/2019
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/21/2023Energization Approved → Sync Approved
- 09/12/2022IA Signed → Energization Approved
- 07/29/2021FIS Requested → FIS Approved
- 07/26/2020FIS Approved → IA Signed
- 03/29/2019Screening → FIS Requested
- 01/03/2019Entered the queue with 234 MW, projected COD 10/31/2026