LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0205 · Solar · Wharton County

Sbranch Solar

Sbranch Solar is a 234 MW solar project in Wharton County, Texas, connecting at Tap 138kV 44190 East Bernard - 44130 Caney. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0205
Capacity
234 MW
Fuel
Solar (PV)
Interconnecting entity
Bernard Creek Solar, LLC
Projected COD
10/31/2026
Entered queue
01/03/2019
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/21/2023
    Energization Approved → Sync Approved
  • 09/12/2022
    IA Signed → Energization Approved
  • 07/29/2021
    FIS Requested → FIS Approved
  • 07/26/2020
    FIS Approved → IA Signed
  • 03/29/2019
    Screening → FIS Requested
  • 01/03/2019
    Entered the queue with 234 MW, projected COD 10/31/2026