21INR0546 · Wind · Eastland County

Anchor Wind III

Anchor Wind III is a 16 MW wind project in Eastland County, Texas, connecting at 345 kV Aspire Station (68011). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/29/2025.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0546
Capacity
16 MW
Fuel
Wind (WT)
Interconnecting entity
RANCHLAND WIND PROJECT LLC
Projected COD
12/29/2025
Entered queue
11/30/2020
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/13/2022
    Energization Approved → Sync Approved
  • 11/29/2021
    IA Signed → Energization Approved
  • 04/30/2021
    Screening → FIS Approved
  • 11/30/2020
    Entered the queue with 16 MW, projected COD 12/29/2025
  • 11/30/2020
    FIS Approved → IA Signed