LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0413 · Solar · Bastrop County

Big Star Solar

Withdrawn

Big Star Solar is a 203 MW solar project in Bastrop County, Texas, connecting at Tap 345kV 9074 Lytton - 9073 Holman. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0413
Capacity
203 MW
Fuel
Solar (PV)
Interconnecting entity
RWE Solar Development, LLC
Projected COD
09/25/2026
Entered queue
08/27/2019
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Listed as withdrawn UNCONFIRMED
  • 12/19/2022
    Energization Approved → Sync Approved
  • 12/06/2022
    IA Signed → Energization Approved
  • 07/19/2021
    FIS Requested → FIS Approved
  • 10/02/2020
    FIS Approved → IA Signed
  • 12/20/2019
    Screening → FIS Requested
  • 08/27/2019
    Entered the queue with 203 MW, projected COD 09/25/2026

Other projects at this substation

Big Star StorageBESS80 MWWithdrawn