ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0391 · Solar · Atascosa County

Grandslam Solar

Grandslam Solar is a 122 MW solar project in Atascosa County, Texas, connecting at 5700 Miracle Lake 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0391
Capacity
122 MW
Fuel
Solar (PV)
Interconnecting entity
Grandslam Solar, L.L.C.
Projected COD
10/01/2027
Entered queue
07/26/2019
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/29/2021
    FIS Requested → IA Signed
  • 07/26/2019
    Entered the queue with 122 MW, projected COD 10/01/2027
  • 07/26/2019
    Screening → FIS Requested