Pecan Prairie South is a 133 MW solar project in Leon County, Texas, connecting at CTT Yellow Wolf, bus # 79007. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0371
Capacity
133 MW
Fuel
Solar (PV)
Interconnecting entity
ConnectGen Operating LLC
Projected COD
05/01/2027
Entered queue
08/16/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/13/2026
    FIS Requested → FIS Approved
  • 02/21/2021
    FIS Approved → IA Signed
  • 08/22/2019
    Screening → FIS Requested
  • 08/16/2019
    Entered the queue with 133 MW, projected COD 05/01/2027

Other projects at this substation

Pecan Prairie NorthSolar324 MWIA Signed