ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0324 · Wind · Navarro County

Board Creek Wind

Board Creek Wind is a 299 MW wind project in Navarro County, Texas, connecting at 345kV 3386 Outlaw Switch. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0324
Capacity
299 MW
Fuel
Wind (WT)
Interconnecting entity
Limestone Wind Project, LLC
Projected COD
10/31/2026
Entered queue
04/24/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/06/2022
    Energization Approved → Sync Approved
  • 09/19/2022
    IA Signed → Energization Approved
  • 04/26/2022
    FIS Requested → FIS Approved
  • 08/19/2021
    FIS Approved → IA Signed
  • 11/05/2019
    Screening → FIS Requested
  • 04/24/2019
    Entered the queue with 299 MW, projected COD 10/31/2026