ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0268 · Solar · Ector County

Greyhound Solar

Greyhound Solar is a 335 MW solar project in Ector County, Texas, connecting at Tap 345kV 11010 Wolf - 1018 Moss. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 06/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0268
Capacity
335 MW
Fuel
Solar (PV)
Interconnecting entity
Rockhound Solar 2, LLC dba "Greyhound Solar"
Projected COD
06/30/2026
Entered queue
03/21/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/24/2026
    Energization Approved → Sync Approved
  • 11/26/2025
    IA Signed → Energization Approved
  • 10/31/2024
    FIS Requested → FIS Approved
  • 01/15/2022
    FIS Approved → IA Signed
  • 03/21/2019
    Entered the queue with 335 MW, projected COD 06/30/2026
  • 03/21/2019
    Screening → FIS Requested